Day 33: Wind Posts installed
The planner has specified windposts which go inside the brickwork on the front wall. There has been a huge delay in getting these completed, which has held up the brickwork quite a bit. They were installed today at last!
Day 26: More Brickwork
The second side wall is completed in the 2nd day of bricklaying. So each side only took a day each. The brickwork goes up so fast with good bricklayers!